The Mill at Freedom Falls - Freedom, Maine
  • Welcome
  • History
  • Team
  • Rehabilitation Process
  • Vision/Use
  • Hydropower
  • Photos
  • Blog
  • Sketches/Plans
  • Contact

July 26, 2012

7/29/2012

2 Comments

 
2 Comments

July 24, 2012

7/25/2012

2 Comments

 
Weeks of July 16 and 23, 2012

Foundation repairs and rebuilding the undercarriage continued despite some new structural problems.  The sills are all in, and Rod and his men are doing a beautiful job on raising the top foundation stones to meet the new, now level, sills.  You would never know the wall had drooped about a foot along the northeast corner.  Half the old roofing has been removed, and “ice and water shield” has been installed.

Joseph and I met with Ed from Arron’s team for a briefing on unanticipated problems:  rot on one of the posts on the water side will necessitate replacement, and water damage from open windows on that side led to squirrels creating nests in the beam!  Both ends of the beam can be saved, preserving the original English tying joints, and the middle will have a new piece of hemlock spliced in.

Our original hydropower estimate of net power generation seems to be within range of the original, as are the cost estimates.  Edwin’s plan looks as if it will require only a small amount of digging out of the foundation floor and uses an exit tailrace outside of the building.

The permits for silt removal and dam repairs will have to be obtained from DEP.  In the meantime we will work on tree removal across the stream for access to that end of the dam.  We plan to walk that next week to lay out the entry road, future septic field and parking lot, as well as mark all trees for removal.   Progress continues!

2 Comments

July 11, 2012

7/25/2012

0 Comments

 
Meetings with Jay, Rob, Chris and then Carmen.  We’re going with window sashes built by Matthews Brothers, which are the closest match to originals, with frames built by CMB’s shop.  We reviewed plans for hydropower and discussed the floor “sandwich”.  We settled on using new hemlock on the first floor, as the old was in bad shape and not that old – all to be cleared by the SHPO, etc. in a couple of weeks.  Solid boards will be used on the floors and sheathing - no plywood.

One of the old millstones was found at a neighbor’s yard.  It’s a precise fit (51 inches in diameter and about 7-1/2 inches thick) to the cutout in the floor joists that we had discovered, so we’ll acquire it.

In a subsequent meeting with Arron, a review of progress showed that the whole first floor support system may be finished by the end of the week.  Beams that had had tenons cut into their ends earlier were being installed, and the foundations capstones were being set up under the new sills all around the mill.  As the wood structure overhangs the foundation because of adding insulation and so forth on the exterior walls, the foundation capstones will be set out about an inch to take up some of the overhang.  The post to the east of the door on the south side is badly rotted and will have to be entirely replaced.

The troops spent lots of time examining the dam and the wheelhouse to develop a plan for the hydro system.
0 Comments

Week of July 9, 2012

7/25/2012

0 Comments

 
Meetings with Jay, Rob, Chris and then Carmen.  We’re going with window sashes built by Matthews Brothers, which are the closest match to originals, with frames built by CMB’s shop.  We reviewed plans for hydropower and discussed the floor “sandwich”.  We settled on using new hemlock on the first floor, as the old was in bad shape and not that old – all to be cleared by the SHPO, etc. in a couple of weeks.  Solid boards will be used on the floors and sheathing - no plywood.

One of the old millstones was found at a neighbor’s yard.  It’s a precise fit (51 inches in diameter and about 7-1/2 inches thick) to the cutout in the floor joists that we had discovered, so we’ll acquire it.

In a subsequent meeting with Arron, a review of progress showed that the whole first floor support system may be finished by the end of the week.  Beams that had had tenons cut into their ends earlier were being installed, and the foundations capstones were being set up under the new sills all around the mill.  As the wood structure overhangs the foundation because of adding insulation and so forth on the exterior walls, the foundation capstones will be set out about an inch to take up some of the overhang.  The post to the east of the door on the south side is badly rotted and will have to be entirely replaced.

The troops spent lots of time examining the dam and the wheelhouse to develop a plan for the hydro system.

0 Comments

Week of July 1, 2012

7/2/2012

1 Comment

 
After two weeks away, we visited the mill today.  Significant progress, though there is much detail work, so it is not as obvious as in the past. The building has been completely leveled, the sag taken out of the north side, etc., and all the sills have been replaced, with joinery fastening the vertical posts into the sills all complete.
Picture
Level with new sills.
Picture
The sills are all notched and ready for the bolsters and floor joists (this process has begun, and one old bolster and one new have been joined to the new sills). Arron reports that the building is now about 1 inch out of square, and we may get that eventually also. He continues to take the “smile” out of the tie beams.
Picture
New sills notched.
Picture
As for the north foundation wall, the door into the basement is framed on its sides and bottom, and the wall is now a couple of feet above the level where the basement floor will be laid under the north addition. The door is nicely positioned to provide easy access down to the top of the old wheelhouse, much of which will remain.
Picture
Basement door under north addition.
1 Comment

Update from Joseph

6/26/2012

1 Comment

 
1 Comment

Progress...

6/22/2012

0 Comments

 
0 Comments

Construction Techniques

6/11/2012

30 Comments

 
Aaron, after the scaffolding was put up right close to the first floor supports, saw that he would want to propose changing the plan for reconstructing the first floor supports that will be much more in keeping with the original layout.  We will have removed three layers of flooring on the first floor, carefully removing what we can save and re-using the good stuff for the underlayment of the floor so it will look as it does today from within the foundation.

By the end of May the deck was built to provide access for building the northern wall.  Rod and his two sons have rigged up a pulley from steel I-beams stretched across scaffolding outside the building.  They move stone onto the deck with the skidder, then drill a hole in the stone, insert a threaded sleeve, then screw in an eye-bolt.  Then they just hoist the stone or granite block and lower it into the hold.  Down there, Rod’s nephew sets the stone in place on wet cement laid on top of the footing.

Picture
After drilling granite with holes, these threaded sleeves are inserted, and into them goes an eye-bolt to which the hoist is attached for lowering the stone into the basement.
Picture
Hoist ready to lower the granite down.
A zip line runs from a locust on the Luhn property through the open west wall, through a northern window and then attaches to a maple down our property toward Pleasant Street.  The zip line lifts the huge hemlock beams and slides them over to the Mill to be set in place.

Another cool thing we saw was an “Archimedes” rig for determining the level of the floor.  Not yet using lasers, so they used a water tube on the second floor to figure out how much each part of the floor needs to be adjusted to have everything level so as to counter sagging of as much as 10 inches.
Picture
"Archimedes" at work. This is the system for determining how much each part of the building needs to be raised to obtain a level floor. No laser technology being used here!
The western wall has steel plates on all the posts, with jacks rigged to the plates.  This is how they lift the whole west wall to slide in new sills.
Picture
West end of original mill building supported by jacks so rotted sill can be removed and replaced.
The next design focus has to be on getting the details set precisely for the turbine installation.  The discovery here is that most of the floor is large stone and rubble, rather than ledge, so placing the penstock has become easier and may not require chipping away at ledge.  This team will have to try to save as much of the old wheelhouse as possible; we will probably be able to save about half of the hole where the old penstock entered as well as the remains of the old turbine to the west of the penstock entry point.

You can see why it’s exciting to be here every step of the way!
30 Comments

Discoveries

6/11/2012

2 Comments

 
Tony has said all along that every time he goes into the Mill, he discovers something new.  These are some examples he has reported:

The most exciting thing we (the team) discussed was the discovery of a circle cut out of the timbers in the undercarriage to house a bedstone.  This had been buried under the floor, which was three or four boards thick in some places.  They obviously just added flooring whenever needed, rather than ripping anything up… Weight was added, holes were drilled, foundation stones were removed, joists were drilled, etc.  It is a real testament to the original design that the building didn’t collapse long ago.  We now want to figure out how to show this area, not burying it again beneath the floor… Glass? I will check with TriPyramid, which helps build the flagship Apple stores.
Picture
After the flooring was removed it revealed these beam rounded out for the bedstone from the grist era.
Back in early April we found a great spot where the belts came up through the floor between first and second floors in the first ell. Before that, surprises came up at every visit… the scribe-rule joinery, the English tying joints over gunstock beams, the old tubs for lacquering the turned handles, etc. The crew has found, as they have cleared the detritus, some interesting equipment such as cutting tools, grinding wheels, and many turned wooden pieces of various shapes and sizes. They also discovered a nameplate on piece of hardware we had been unable to identify.  I later discovered that it was a dowel maker from W. S. Hawker Mfg. Co. of Dayton, Ohio.
Picture
The dowel making machine is pictured to the right.
2 Comments

The Mill

6/7/2012

2 Comments

 
You come upon this wonderful old sleeping reminder of the past as you turn into the quiet corners of Freedom Village on the way to Village Farm.  It fairly speaks -- silently -- of the past.  You can almost smell the fresh sawdust, touch the rough lumber or sift the grains through your hands, see the millstones turning… But it’s the SOUND of the force that powered all that, the water! that is here, not just an echo but alive, a dimension, ready to lend life again to The Mill and the Village of Freedom.  Now, just as it has for who knows how many years, the water plunges down the dam from that quiet millpond and courses through to Sandy Stream, bringing the natural force of its strength beneath the mill structure.  Its sound is pervasive.  Hearing it brings alive the vision of restoring the vitality this stream once brought to daily life In Freedom. It is a life force for the creatures that live within the stream and pond: a beaver swims in the millpond, loons cry out from Sandy Pond (aka Freedom Pond) upstream, geese land on the intermediate “duck pond” as they return from their winter homes to the south, elvers – young eels -- find their way up to and around the dam as they migrate from the Sargasso Sea in the middle of the North Atlantic Ocean where they were spawned. But the stream is also a life force for the community of humans, who gathered there in the early 18th century to carve a life out of the wilderness, who relied on the river for their subsistence and their income, who abused the river because it seemed indestructible and who now appreciate it for its beauty and reviving wildlife.

The Mill expresses the promise of the past when it, like so much of the country that depended on river power, was part of the thriving community.  It’s just waiting for the renewal of a familiar life.  Hearing the constant sound of the water, you can listen for the voices of old-timers who today remember the place this mill held in the vitality of their eras as they recall their memories for the interviewers who are recording this renewal on film.  The Mill is a stage, returning many of the props of those days to renewed use; it stirs the figurative wheels of imagination.  Listen to the echoes and think of the restoration that has already taken the lead in bringing back that energy that held such a vital part in the development of this land.

It was the realization that this mill and power source could be restored without compromising the river environs that prompted our investigating the possibilities. Only later did we become so thoroughly enchanted by the history of the mill and its original construction that has withstood the ravages of time and intensive use and abuse. That it is still standing at all is a tribute to those who designed and built it without the benefit of power equipment. They built it to withstand the vibrations of three grinding wheels, and it has done that and more.
2 Comments
<<Previous
Forward>>

    Author

    This blog follows the process of rehabilitating the mill and restoring hydropower to the dam at Freedom Falls in Freedom Maine.

    Archives

    September 2020
    January 2017
    November 2015
    January 2015
    May 2014
    December 2013
    September 2013
    July 2013
    June 2013
    May 2013
    April 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012

    Categories

    All

    RSS Feed

Copyright © Tony & Sally Grassi 2012. All rights reserved. www.millatfreedomfalls.com
Powered by Create your own unique website with customizable templates.